Honnold/Mudd Library Construction Projects
Re-roofing:
We are pleased to announce that the project to provide a new roof
for Honnold/Mudd Library is nearing completion! The re-roofing
began on October 16, 2003 and is now seventy-five percent complete.
Parts of the roof are being replaced, which will protect us and
our resources. Most of the remaining work will not involve the
noise disturbances of heavy demolition; furthermore, the heating,
ventilation and air conditioning system (HVAC) will no longer
need to be turned off, ensuring a comfortable climate within
the library. The remaining work will in large part be focused
on the portion of the roof which covers the Search Center (Mudd
side of the library) and will be the most complex portion of
the project due to the close proximity of telephone antennas
and vertical cement columns found on this area of the roof.
We would like to thank all patrons of Honnold/Mudd Library for
your continued support and understanding during this re-roofing
project. We will continue to do all that we can to alleviate any
inconveniences caused by the project.
Circulation Redesign:
During December and January, the entire Circulation area was redesigned
and renovated to provide better service, to improve behind-the-scenes
work flow for staff and to use the available space more efficiently.
In addition to a new public service counter and new carpeting
and paint, new furnishings and upgraded computers will allow
a smoother check-out and check-in process, for both library users
and staff. The equipment will provide separate work areas for
specific functions, such as the processing of Link+ books and
ERes (Electronic Reserve) materials. In the near future, we will
also add a new Self-Checkout machine that will allow patrons
to check out their own books without staff mediation.
Additional Construction Updates:
The sidewalk on the south side of the library which extends from
Columbia to Dartmouth Avenue is now reopened. It was closed due
to the digging of two new manholes, which are now complete.
The bookdrop on the east side of Honnold/Mudd, which had been
temporarily moved during construction, has now been moved back
to its original location on the corner of Columbia and 8th Street.
Linda Gunter
Honnold/Mudd
linda.gunter@libraries.claremont.edu
Ray Martinez
Honnold/Mudd
ray.martinez@libraries.claremont.edu
|